A
Abe
I'm trying to create an XML based MS Project and but I'm having trouble
setting the percent complete for the task. I'm giving the task a
<start>,<finish>, <actualstart>, and <percentcomplete> but its not working
and when the project is opened, the percent complete is always 0% (unless I
give an actual finish in which case its 100%). It seems to want an
<actualduration>, but I thought it can calculate this based on percent
complete and actualstart...
Am I missing something?
setting the percent complete for the task. I'm giving the task a
<start>,<finish>, <actualstart>, and <percentcomplete> but its not working
and when the project is opened, the percent complete is always 0% (unless I
give an actual finish in which case its 100%). It seems to want an
<actualduration>, but I thought it can calculate this based on percent
complete and actualstart...
Am I missing something?