How do you set tasks that go on throughout the project duration?

A

Al

I want to set tasks such as risk management, that go on for the entire
duration of the project, but do not affect the project length or the critical
path.
 
A

aaren

Hi Al,

In every project there are activities which are managerial in nature
and the way I have handled them is by providing 'buckets' for their
activities.

What I did was to create an Activity called 'Management Functions' to
cover : Risk Management, Project Direction, Project Updation (this
includes the time for reporting from Project Manager / Project Control
Office), Infrastructure Activities and similar activities. The overall
activity of Management Functions' will be within the plan but is
'outside' the scope of main project activities.

Hope this helps.
 
M

Mike Glen

Hi Al,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 