how do you set up the resource pool?

D

Dale Howard [MVP]

twestbrook --

Do the following:

1. Open Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Resource Pool
3. Since no resources currently exist, simply click the Open/Add button
4. Enter your resources and all relevant information about them
5. Double-click each resource to enter their network user ID information
and e-mail address
6. Save and close the Enterprise Resource Pool

Hope this helps.
 