P
Projectina
...available for project work?
In other words, by default Project has an 8 hour work day. While tha
is nice, we all know no one puts in all 8 hours into their assignment
between meetings, phone calls, breaks, etc.
So lets say I want 6 of 8 hours a day towards project work... As
see it, my options are:
1) Change the project calendar to be from 8am to 3pm or 9am to 4pm
etc. so that each day is 6 hours long
2) Change each resources max units to 75% and leave the projec
calendar at 8 hour days
3) Change each resource calendar to show that they only work 6 hou
days, but leave their max units at 100% and the project calendar at
hour days
4) Leave all the defaults and just change the resource assignmen
units to 75% on each task assignment
Let me know if I'm missing an option.
#1 - I don't like it as much because I prefer to always see a 40 hou
week and imagine it can be better for material resources in some cases
#2 - Seems to be the best since you can change some resources as neede
if they really can be devoted all day
#3 - Seems nice too but too much work maintaining each resourc
calendar and also feels somewhat artificial
#4 - Greatest flexibility but a nightmare to maintain
What do most of you find works best to take into account a real wor
day
In other words, by default Project has an 8 hour work day. While tha
is nice, we all know no one puts in all 8 hours into their assignment
between meetings, phone calls, breaks, etc.
So lets say I want 6 of 8 hours a day towards project work... As
see it, my options are:
1) Change the project calendar to be from 8am to 3pm or 9am to 4pm
etc. so that each day is 6 hours long
2) Change each resources max units to 75% and leave the projec
calendar at 8 hour days
3) Change each resource calendar to show that they only work 6 hou
days, but leave their max units at 100% and the project calendar at
hour days
4) Leave all the defaults and just change the resource assignmen
units to 75% on each task assignment
Let me know if I'm missing an option.
#1 - I don't like it as much because I prefer to always see a 40 hou
week and imagine it can be better for material resources in some cases
#2 - Seems to be the best since you can change some resources as neede
if they really can be devoted all day
#3 - Seems nice too but too much work maintaining each resourc
calendar and also feels somewhat artificial
#4 - Greatest flexibility but a nightmare to maintain
What do most of you find works best to take into account a real wor
day