How do you show percent complete on the task form?

P

Phil

When looking at a split screen Gantt chart/Task form how do we customize the
task form to show Percent complete for predecessors and successors. It seems
that the status of the tasks related to the one selected would be important
to see but how to do this is not obvious.
 
D

Darrell

Phil,

If you double click the Predecessor or Successor task name it will open the
task information box which shows the % complete. Only way I know to see it.

Darrell
 