M
MPPer
I need to "zero-out" a task instead of removing it. How would that be done?
MPPer said:I need to "zero-out" a task instead of removing it. How would that be done?
MPPer said:I need to "zero-out" a task instead of removing it. How would that be done?
MPPer --
From your question, I assume that you are referring to tasks that have no
Actual Work entered against them, and that you can to cancel the tasks
because they are no longer needed in the project. Assuming this to be the
case, I prefer to use a method such as the following:
1. Open the project in question.
2. Apply the Gantt Chart view.
3. Click View - Table - Work.
4. Set the Remaining Work to 0 hours for the task you want to cancel.
5. Double-click the task and then click the Notes tab.
6. Add a Note documenting the reason for cancelling the task, and then
click the OK button.
In the above set of steps, setting the Remaining Work to 0h will change the
Duration to 0d, which will cause the software to display the Gantt bar for
the task as a Milestone symbo (black diamond). So, I prefer to continue the
steps by doing the following as well:
7. Double-click the Milestone symbol for the cancelled task.
8. In the Format Bar dialog, click the Shape pick list in the Start section
and choose a different symbol to represent cancelled tasks.
9. Click the OK button.
When you begin using custom symbols to represent cancelled tasks, you will
need to communicate the meaning of this symbol to all parties interested in
your project. Just a thought. Perhaps the others will have ideas for you
as well.
MPPer --
From your question, I assume that you are referring to tasks that have no
Actual Work entered against them, and that you can to cancel the tasks
because they are no longer needed in the project. Assuming this to be the
case, I prefer to use a method such as the following:
1. Open the project in question.
2. Apply the Gantt Chart view.
3. Click View - Table - Work.
4. Set the Remaining Work to 0 hours for the task you want to cancel.
5. Double-click the task and then click the Notes tab.
6. Add a Note documenting the reason for cancelling the task, and then
click the OK button.
In the above set of steps, setting the Remaining Work to 0h will change
the
Duration to 0d, which will cause the software to display the Gantt bar for
the task as a Milestone symbo (black diamond). So, I prefer to continue
the
steps by doing the following as well:
7. Double-click the Milestone symbol for the cancelled task.
8. In the Format Bar dialog, click the Shape pick list in the Start
section
and choose a different symbol to represent cancelled tasks.
9. Click the OK button.
When you begin using custom symbols to represent cancelled tasks, you will
need to communicate the meaning of this symbol to all parties interested
in
your project. Just a thought. Perhaps the others will have ideas for you
as well.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.