D
del
Hi, I'm new at this so bear with me if this seems simple:
I have a series of tasks assigned to a single resource and I want to
know in which order to complete the tasks.
To understand this better I created a new project of 2 tasks of 2
days, assigned to 1 resource.
The 1st task's priority is 500, the second's 600. Right now both tasks
are assigned to the resouce at once and the resource is overallocated
(200% each day)
What I would assume, when I hit level resource, is to see task#2 last
for 2 days THEN task#1 (with a lower priority) to follow for the next
2 days.
But no.
What am I missing?
Thank in advance.
I have a series of tasks assigned to a single resource and I want to
know in which order to complete the tasks.
To understand this better I created a new project of 2 tasks of 2
days, assigned to 1 resource.
The 1st task's priority is 500, the second's 600. Right now both tasks
are assigned to the resouce at once and the resource is overallocated
(200% each day)
What I would assume, when I hit level resource, is to see task#2 last
for 2 days THEN task#1 (with a lower priority) to follow for the next
2 days.
But no.
What am I missing?
Thank in advance.