How does MS Project compute resource units %

S

ST

Hi,

Can someone tell me how MS Project is calculating '% complete' in this
scenario...


I have a 4 week fixed duration task with a resource at 50%. Then, I set the
task to 50% complete. Then I change the resource units to a value less than
50%. The remaing work revises accordingly, but the resource units remains at
50%. If I revise the resource units to more than 50% then it displays the
units entered. It is only when I enter less than 50% that it does not
display the value, yet it always adjusts the remaining work accordingly. How
or why does the resource units not display accurately when there is task %
complete? Any ideas welcomed.

Thanks.
Spiro Theopoulos
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top