R
rhino
I suspect Microsoft Project is NOT doing a full PERT to beta
distribution and then applying the central limit theorem.
It does seem to be using the three durations (optimistic + 4x expected
+ pessimistic all over 6) to determine a weighted average for each
task, and then it adds up all those tasks on the critical path to
determine the nominal value for the whole project.
But when it works out the pessimistic (optimistic) value for the whole
project it seems to use ALL the pessimistic (optimistic) values, which
lacks statistical robustness. The correct way to do it would be to
determine the variance of the whole project, and then use the normal
distribution to determine the 90% confidence interval for total project
duration. I can see no evidence that MS Project is actually doing this.
Can anyone else put some light on this topic?
distribution and then applying the central limit theorem.
It does seem to be using the three durations (optimistic + 4x expected
+ pessimistic all over 6) to determine a weighted average for each
task, and then it adds up all those tasks on the critical path to
determine the nominal value for the whole project.
But when it works out the pessimistic (optimistic) value for the whole
project it seems to use ALL the pessimistic (optimistic) values, which
lacks statistical robustness. The correct way to do it would be to
determine the variance of the whole project, and then use the normal
distribution to determine the 90% confidence interval for total project
duration. I can see no evidence that MS Project is actually doing this.
Can anyone else put some light on this topic?