A
amc422
The status column indicates if a task is late, on schedule, future task,
etc., using numeric values. To what do those numeric values relate? I
thought the values related to SPI, but that does not appear to be the case.
The numbering scheme used is:
0 = complete
1 = on schedule
2 = late
3 = future task
SPI values:
Greater than 1 = ahead of schedule
Less than 1 = behind schedule
So what do the numbers on which Project determines whether or not a task is
late mean? Also, how does project calculate this value for rollup tasks?
Many thanks,
Anna
etc., using numeric values. To what do those numeric values relate? I
thought the values related to SPI, but that does not appear to be the case.
The numbering scheme used is:
0 = complete
1 = on schedule
2 = late
3 = future task
SPI values:
Greater than 1 = ahead of schedule
Less than 1 = behind schedule
So what do the numbers on which Project determines whether or not a task is
late mean? Also, how does project calculate this value for rollup tasks?
Many thanks,
Anna