P
Patrick Peters
I'm running project 2000. I'm putting together a project where I am
assigned to multiple tasks that have no contraints for start or finish time.
There are more requests for my time than there hours in the day, so
levelling pushes some of the dates out to fix the resource allocation.
When project has multiple tasks competing for the same resource, how does it
decide which task "wins"? I've tried raising the priority of the task, but
that doesn't seem to affect behavior.
Thanks
Pat
assigned to multiple tasks that have no contraints for start or finish time.
There are more requests for my time than there hours in the day, so
levelling pushes some of the dates out to fix the resource allocation.
When project has multiple tasks competing for the same resource, how does it
decide which task "wins"? I've tried raising the priority of the task, but
that doesn't seem to affect behavior.
Thanks
Pat