J
jpa
PS2007, SP1, CU
Hi there I am completely lost with Project Server regarding Assignment
Baseline Work?
I'd like to generate a report (using Reporting Services) which gives per
Project, per Task, per Resource, on a day by day basis, planned work and
actual work.
Actual work is retrieved within MSP_EpmAssignmentByDay.AssignmentActualWork
field.
Where to find the Planned work?
I had a look at MSP_EpmAssignmentByDay_UserView.AssignmentBaseline0Work but
unfortunately this field is not systematically filled!
I browsed the database and I found that in very few cases this field
contained some data...most of the time it is NULL or set to 0.
I cannot find any logic! (I don't think there diffrerent ways to set a
baseline...)
Thanks for your help
Hi there I am completely lost with Project Server regarding Assignment
Baseline Work?
I'd like to generate a report (using Reporting Services) which gives per
Project, per Task, per Resource, on a day by day basis, planned work and
actual work.
Actual work is retrieved within MSP_EpmAssignmentByDay.AssignmentActualWork
field.
Where to find the Planned work?
I had a look at MSP_EpmAssignmentByDay_UserView.AssignmentBaseline0Work but
unfortunately this field is not systematically filled!
I browsed the database and I found that in very few cases this field
contained some data...most of the time it is NULL or set to 0.
I cannot find any logic! (I don't think there diffrerent ways to set a
baseline...)
Thanks for your help