W
Wegz
Hi.
I hope someone can help me. I want another system to get data out of
our project server database. It needs to be able to get data on a
resource and show the resource's total hours per day on a project.
(basically like the timesheet view in resource usage)
This will then allow us to assign flags to determine what actual days
have been paid for or accured for our finance system. Its so we can
keep track of the costs being billed to us for contractors etc.
Now the only work values i can find in the database are total values.
EG. PROJECT 130 TASK ID 22 ACTUAL WORK 10 HOURS.
Is there somewhere in the databases that shows the timephased values:
eg.PROJECT 130, TASK ID 22 RESOURCE 4 --> DATE 1 WORK 2 HOURS; DATE 2
WORK 1 HOUR; DATE 3 WORK 7 HOURS?
Thanks.
Matthew
I hope someone can help me. I want another system to get data out of
our project server database. It needs to be able to get data on a
resource and show the resource's total hours per day on a project.
(basically like the timesheet view in resource usage)
This will then allow us to assign flags to determine what actual days
have been paid for or accured for our finance system. Its so we can
keep track of the costs being billed to us for contractors etc.
Now the only work values i can find in the database are total values.
EG. PROJECT 130 TASK ID 22 ACTUAL WORK 10 HOURS.
Is there somewhere in the databases that shows the timephased values:
eg.PROJECT 130, TASK ID 22 RESOURCE 4 --> DATE 1 WORK 2 HOURS; DATE 2
WORK 1 HOUR; DATE 3 WORK 7 HOURS?
Thanks.
Matthew