M
mh_amri
hi
i am new to msp 2007 and in fact i am a student which learning project
management with msp.
in one homework we have
{task (duration)} & {">" : "A>B" mean after finish A , B could start}"
A(2)>E(3),F(2),C(1)
E(3),F(2),C(1),B(4)>D(5)
limit in pipe(material) is like below
in the morning of 1st week : 300 meter pipe number 4
" " " " " " " " " " 3rd week : 350 meter pipe number 10
" " " " " " " " " " 5th week : 400 meter pipe number 4
" " " " " " " " " " 8th week : 50 meter pipe number 10
" " " " " " " " " " 8th week : 400 meter pipe number 4
and task "A" need 200 meter pipe 6
and task "B" need 300 meter pipe 4
and task "C" need 100 meter pipe 6
and task "D" need 500 meter pipe 4
adn task "E" need 300 meter pipe 10
and task "F" need 100 meter pipe 10
wow! i typed too much
now the problem is msp can't accept limit and float material
[in Res.sheet>resource inf. the resource availability is unactive (]
so how can i solve this practice and tell the msp i have a limited material
availabilty ?
indeed the goal of this practice is "Leveling"
if you read till here you really want to help me , so thank you very very
much!
i am new to msp 2007 and in fact i am a student which learning project
management with msp.
in one homework we have
{task (duration)} & {">" : "A>B" mean after finish A , B could start}"
A(2)>E(3),F(2),C(1)
E(3),F(2),C(1),B(4)>D(5)
limit in pipe(material) is like below
in the morning of 1st week : 300 meter pipe number 4
" " " " " " " " " " 3rd week : 350 meter pipe number 10
" " " " " " " " " " 5th week : 400 meter pipe number 4
" " " " " " " " " " 8th week : 50 meter pipe number 10
" " " " " " " " " " 8th week : 400 meter pipe number 4
and task "A" need 200 meter pipe 6
and task "B" need 300 meter pipe 4
and task "C" need 100 meter pipe 6
and task "D" need 500 meter pipe 4
adn task "E" need 300 meter pipe 10
and task "F" need 100 meter pipe 10
wow! i typed too much
now the problem is msp can't accept limit and float material
[in Res.sheet>resource inf. the resource availability is unactive (]
so how can i solve this practice and tell the msp i have a limited material
availabilty ?
indeed the goal of this practice is "Leveling"
if you read till here you really want to help me , so thank you very very
much!