JR
We just setup Microsoft Project Server 2003. Project Manager is not
currently creating Enterprise projects as we have not figured out how
to do that yet. He uploads a project to project server with resource
names that match exactly the full names of the users in the project
server. It does not seem to link the MS project file resources with
the users defined in Project Server, so when a resource connects in,
they are told they have no tasks even though that is not the case. How
do you get Project Server to link the users in their project file with
the users in Project Server?
Thanks.
JR
currently creating Enterprise projects as we have not figured out how
to do that yet. He uploads a project to project server with resource
names that match exactly the full names of the users in the project
server. It does not seem to link the MS project file resources with
the users defined in Project Server, so when a resource connects in,
they are told they have no tasks even though that is not the case. How
do you get Project Server to link the users in their project file with
the users in Project Server?
Thanks.
JR