how percent complete is calculated for nested summary tasks

G

greg

I remember a Microsoft tech document published in the mid
90's that explains the algorithm used by Microsoft to
calculate percent complete for nested summary tasks. Can
anyone direct me to the latest version of it? and will the
same logic apply to the rollup of %complete in grouped
tasks?
 
R

Rod Gill

Hi,

I think it's something like total actual duration complete / Total Duration

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
G

Gérard Ducouret

Hello Greg,

The % Complete is a % in duration (there is also a % Work Complete).
At the Summary level,the % Complete is the ratio between the sum of Actual
Duration of sub-tasks and the sum of the scheduled Durations of these
sub-tasks.

Gérard Ducouret
 