P
Peter Rooney
Good morning,
Some of you may have seen my earlier post on this subject (and avoided it
like the plague, if you had any sense!)
Within an existing plan, where the calendar options are set to
09:00-17:30/7.5 hours per day/37.5 hours per week, and where all resources'
calendars are set to the same i.e. 09:00-13:00 and 14:00-17:30 (7.5 hours), I
want to see what the knock on effect on project durations and end dates would
be of reducing the working day from 7.5 hours to 5.5 hours.
This is because we're now making a more sensible assumption that people only
actually work on projects for 5.5 hours of a 7.5 hour day, the remainder
being taken up with interruptions, comfort breaks etc.
However, I'm not sure if I should do this via Tools Options Calendar, or by
shortening the working day on specific resources' calendars - or both, and if
so, in what order?
Thanks in advance for your help!
Pete
Some of you may have seen my earlier post on this subject (and avoided it
like the plague, if you had any sense!)
Within an existing plan, where the calendar options are set to
09:00-17:30/7.5 hours per day/37.5 hours per week, and where all resources'
calendars are set to the same i.e. 09:00-13:00 and 14:00-17:30 (7.5 hours), I
want to see what the knock on effect on project durations and end dates would
be of reducing the working day from 7.5 hours to 5.5 hours.
This is because we're now making a more sensible assumption that people only
actually work on projects for 5.5 hours of a 7.5 hour day, the remainder
being taken up with interruptions, comfort breaks etc.
However, I'm not sure if I should do this via Tools Options Calendar, or by
shortening the working day on specific resources' calendars - or both, and if
so, in what order?
Thanks in advance for your help!
Pete