D
David Thielen
Hi;
What's the recomended procedure for the following. I am tracking a
software project. We have it all scheduled out and are now working. It
seems to me we want 2 schedules though:
1) The original one where we measure predicition vs actual. This one
should not change - or maybe have along with predicted, actual start
date, end date, & time required.
2) An adjusted one so we see what the most likely completion date is
taking in to account when each task was actually completed.
What is the best way to do this? Turn it in to two project files?
thanks - dave
david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com
Cubicle Wars - http://www.windwardreports.com/film.htm
What's the recomended procedure for the following. I am tracking a
software project. We have it all scheduled out and are now working. It
seems to me we want 2 schedules though:
1) The original one where we measure predicition vs actual. This one
should not change - or maybe have along with predicted, actual start
date, end date, & time required.
2) An adjusted one so we see what the most likely completion date is
taking in to account when each task was actually completed.
What is the best way to do this? Turn it in to two project files?
thanks - dave
david@[email protected]
Windward Reports -- http://www.WindwardReports.com
me -- http://dave.thielen.com
Cubicle Wars - http://www.windwardreports.com/film.htm