ksharman
We have just started using the MS project server 2003 with Project 2003
clents for the PM's. We have noticed that if you link two tasks
together as say Finish to Start, Task A first and Task B next, then the
overdue alerts to team members are not as we expected them to be. For
example, if the resource is overdue in finishing Task A and has not
completed that task yet on PWA, the team member for Task B is still
getting alerts that their task has started -and in some cases - that
Task B is overdue. I understand that project is just using the
information that is has been given so maybe if there is no event from
the user (or manager) to work with, it is just using it predefined plan
and sending
the alerts as we have configured in the PWA view. But is this how it
should work? We would like for the Team member of task B to not
receive the overdue alerts since the linked task A before it is not
done yet but is the best way for this to happen by letting the PM's
update the task dates realistically for overdue tasks within the
Project Pro interface so that the linked tasks after those will have
the desired cascading effect and stop the 'unnecessary' emails?
Thanks for your advice
ksharman
clents for the PM's. We have noticed that if you link two tasks
together as say Finish to Start, Task A first and Task B next, then the
overdue alerts to team members are not as we expected them to be. For
example, if the resource is overdue in finishing Task A and has not
completed that task yet on PWA, the team member for Task B is still
getting alerts that their task has started -and in some cases - that
Task B is overdue. I understand that project is just using the
information that is has been given so maybe if there is no event from
the user (or manager) to work with, it is just using it predefined plan
and sending
the alerts as we have configured in the PWA view. But is this how it
should work? We would like for the Team member of task B to not
receive the overdue alerts since the linked task A before it is not
done yet but is the best way for this to happen by letting the PM's
update the task dates realistically for overdue tasks within the
Project Pro interface so that the linked tasks after those will have
the desired cascading effect and stop the 'unnecessary' emails?