How the calendar option appear in the "Tools -> Option" is different the calendar defined in the "To

K

ks2008

How the calendar option appear in the "Tools -> Option" is different the
calendar defined in the "Tools -> Change Work Time " ?

Thanks
KS
 
R

Rod Gill

Are you talking about the Start and finish times? These are default times if
you enter a Start or finish date (which isn't recommended unless you have
to).

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
K

ks2008

Rod Thanks for ypur response.

Here is my question.
You have Project calendar, Task calendar and Resource Calendar, all
these calendars are defined with start time and end time.

My understanding is, one of these calendar will be applied in
scheduling, hence what is need for the calendar found at
"Tools->option" ?
What is the significance ? why we need this ? What is the priority over
other calendar ?

thanks
KS
 
S

Steve House

The calendars found in Tools/ChangeWorkingTime are where you define the
hours of work, the so-called "base calendars." You pick one of these to
serve as the Project Calendar, essentially the description of the default
working times.

To undertand the Tools/Options settings, first understand that ALL date
fields are actually date/time field, regardless of whether a date format is
chosen where times are displayed or not. When you manually type an entry
into a "start" field but do not actually type the time, Project must make an
assumption as to what time you mean. That assumption is defined by the
"Default Start Time" (or "Default End Time") entries. IMHO these should
normally agree with the start and end of your workday but there's nothing
that says they must agree. It's especially important to note the setting
them DOES NOT change the working time calendar.

Likewise the "Hours per Day", "Hours per Week", and "Days per Month"
settings. Durations are stored and computed in minutes. When you enter a
duration in some other unit - let's say "3 days" - Project must convert that
into minutes for storage and processing. Likewise when it displays
duration - say, in the Gantt chart task table - it must convert back from
minutes which it's been using internally into the units you prefer to see.
Those three settings are the conversion factors it applies to make the
transformation. Again, they usually should agree with the length of your
normal workday and workweek but there's nothing written in stone that says
they must always agree. Most importantly, changing them DOES NOT change the
length of the workday as reflected by the start and finish times in the
Project calendar.

In fact, nothing on that page changes ANYTHING in any of the calendars used
to schedule the project's tasks.
 
M

Mike Glen

Hi KS,

In view of your recent postings, it sounds to me that you need to attend an
introductory course on Project. 2 days would be a minimum. Project is not
easy to pick up an run with like Word or Excel. There's a steep learning
curve to climb which a good course could help you.

Meanwhile, you might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top