P
Peter Williams
What is the best way to accomplish the following ? I have a large project (1
year) with 5 main phases/components (i.e. Soft Dev, Security,
Infrastructure..etc). There is a total budget and each phase has a fixed %
of the total. This includes man hour estimates. Anyway...each Phase will be
made up of several different projects as the year progresses.
If I want to view how the overall project is doing by Phase do I create a
Master project with these 5 Phases and then insert subprojects as necessary
under each phase and publish to Project Server ? Is this the only way to
make sure the numbers (progress %, cost, etc) from the individual projects
will roll up to each Phase of the main project ?
I tried another technique in Project Server by adding a custom project field
which held a "project type" value (Soft Dev, Security, Infrastructure, etc.)
and then created a Project Center view which grouped by project type.
So..all Soft Dev projects showed under the Soft Dev grouping, all Security
projects under Security, etc. This looked nice but this method doesn't roll
up numbers (cost, duration, etc.).
I hope this is clear. Thanks in advance.
Peter
I tried another technique to display
year) with 5 main phases/components (i.e. Soft Dev, Security,
Infrastructure..etc). There is a total budget and each phase has a fixed %
of the total. This includes man hour estimates. Anyway...each Phase will be
made up of several different projects as the year progresses.
If I want to view how the overall project is doing by Phase do I create a
Master project with these 5 Phases and then insert subprojects as necessary
under each phase and publish to Project Server ? Is this the only way to
make sure the numbers (progress %, cost, etc) from the individual projects
will roll up to each Phase of the main project ?
I tried another technique in Project Server by adding a custom project field
which held a "project type" value (Soft Dev, Security, Infrastructure, etc.)
and then created a Project Center view which grouped by project type.
So..all Soft Dev projects showed under the Soft Dev grouping, all Security
projects under Security, etc. This looked nice but this method doesn't roll
up numbers (cost, duration, etc.).
I hope this is clear. Thanks in advance.
Peter
I tried another technique to display