Dear all,
In PWA, as a Project Manager, when I go to Server Setting, then Manage Views
and select "My Work" in order to manage the view of "My Tasks" for any users,
It seems some fields are not available like the "Baseline Finish" or "HREF".
However, they do appear on "Project" for GANT purpose.
As I need to customize My Task view, how is it possible to add this fields?
Thanks for your reply,
P.S I use 2007 SP1, cannot migrate to SP2 cause of many errors with our
architecture IT.