Dear all,

In PWA, as a Project Manager, when I go to Server Setting, then Manage Views
and select "My Work" in order to manage the view of "My Tasks" for any users,
It seems some fields are not available like the "Baseline Finish" or "HREF".
However, they do appear on "Project" for GANT purpose.
As I need to customize My Task view, how is it possible to add this fields?

Thanks for your reply,

P.S I use 2007 SP1, cannot migrate to SP2 cause of many errors with our
architecture IT.
 
A

Andrew Lavinsky

1) Check if you can create a new Enterprise Date field with the formula "=[Baseline
Finish]" and set it to roll down to the assignment level.

2) In a number of SP1 environments that I've worked with, you cannot roll
formula fields down to the assignment level. If that is the case, you need
to create a macro in MS Project to copy Baseline Finish to your new enterprise
field on the save event. If the field is set to roll down, you should be
able to add it to My Tasks.


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top