How to add Remaining (duration) field to Timesheet view in 2007

P

PP

Hi all,

I have tried different things but I did not succeed to add remaining
duration field to the timesheet view so that the resource can adapt the
remaining duration field when he enters times.

I would really appreciate if someone could tell me what are the different
steps to add this field to the Timesheet view in PWA?
Do I have to create a new field or can I use the existing remaining duration
field?
Do I have to create it in Project Professional or in PWA?

Thanks in advance

PP
 
D

Dale Howard [MVP]

PP --

You cannot add Remaining Duration to the Timesheet view in Project Server
2007. Instead, you must add the column to the My Assignments view. Hope
this helps.
 
P

PP

Thanks Dale for the quick answer.

Does this also apply to Remaining Work field?
Only via My assignments view?

Thanks for the answer.

PP
 
D

Dale Howard [MVP]

PP --

Yes.





PP said:
Thanks Dale for the quick answer.

Does this also apply to Remaining Work field?
Only via My assignments view?

Thanks for the answer.

PP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top