The "Tied Timesheet" code corrects some of the clunkyness with the
Timesheet
process (sorry.. no remaining work). You can find it on Codeplex. I've
got 2 customers that like it - installation is a bit tricky.
:
Hi TIBA,
what I do know is that MS knows of the gaps that the current timesheet
has
and I am certain that the next release will close many ( all?) gaps. To
when
the next realese comes out, I am not sure. I guess no one knows yet
--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
:
Marc,
Thank you for the quick response. Do you know of any plans to include
more
flexibility in the timesheet view in future releases?
Thanks!
-- TiBA
:
Hi TiBA,
Unfortunalty you cant. If you want to update remaining work from the
timesheet, what you will need to do is click on the task name within
the
timehseet. An extra window will open up with the task details, here
you can
update the remaining work.
I know that is not very nice and clunky, but at this point in time
you
cannot add the remaining work column into the timesheet.
Sorry to say
--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
:
I am using MS Project Professional 2007, Project Server 2007 and
Project Web
Access (PWA) 2007.
How do I add columns such as Remaining Work to the timesheet view
in PWA
2007? On my Timesheet View, only four columns are available: Cost
Type
[Resource], Health [Task], RBS [Resource], Team Name [Resource]. I
have full
Admin privileges.
Thanks!