C
circle10
hi i'm trying to form a network diagram but i need to adjust the dates that i
have
such as the 20/08/2008 as my start date to adjust to 0 days and my EST
(Early Finish Time) as 5 days LST (Late Sart Time) as 4 days instead of
24/08/2008.
Any suggestions would be greeatly appreciated
have
such as the 20/08/2008 as my start date to adjust to 0 days and my EST
(Early Finish Time) as 5 days LST (Late Sart Time) as 4 days instead of
24/08/2008.
Any suggestions would be greeatly appreciated