P
Philippe
Hi,
I am trying to allocate resources to each task. Some of my
tasks consume more than one person, but I would like to be
able to allocate the resources in such a way that, when
looking at the resource graph, it displays the resources
separately. For instance:
The task: Detailed analysis
The resources: John, Peter
Duration: 2 months
Peter is also assigned to another task at that same time.
When looking at the graph currently, it shows "John,
Peter" as if they were one single resource
John, Peter: 2 months / 100%
Peter: 2 months / 100%
(overallocation = 0)
when what I really need is:
John: 2 months / 100%
Peter: 2 months / 200%
Do you know how to do that without breaking the tasks
themselves into 2 separate tasks?
Thanks a lot
Philippe
I am trying to allocate resources to each task. Some of my
tasks consume more than one person, but I would like to be
able to allocate the resources in such a way that, when
looking at the resource graph, it displays the resources
separately. For instance:
The task: Detailed analysis
The resources: John, Peter
Duration: 2 months
Peter is also assigned to another task at that same time.
When looking at the graph currently, it shows "John,
Peter" as if they were one single resource
John, Peter: 2 months / 100%
Peter: 2 months / 100%
(overallocation = 0)
when what I really need is:
John: 2 months / 100%
Peter: 2 months / 200%
Do you know how to do that without breaking the tasks
themselves into 2 separate tasks?
Thanks a lot
Philippe