V
VD
I was given this question:
Suppose only six workers are available at any one time for the duration of
the project. Given the same start date and 6-day work week from Question Set
1, above, allocate workers to finish the project as quickly as possible. Make
sure no more than six workers are being used at once!
What I want to know is how can I allocate only six workers to be available
at once? So once a task is finished that worker goes on to the next available
task while the others are still working on other tasks
Suppose only six workers are available at any one time for the duration of
the project. Given the same start date and 6-day work week from Question Set
1, above, allocate workers to finish the project as quickly as possible. Make
sure no more than six workers are being used at once!
What I want to know is how can I allocate only six workers to be available
at once? So once a task is finished that worker goes on to the next available
task while the others are still working on other tasks