How to assign people to task "As needed"

A

Al

What would be the best way to assign a resource as needed. I am working on a
project and there are some tasks that people would be assigned to as needed;
they may spend 1% of there time or sometimes 50%, etc.
thanks
Al
 
R

Rod Gill

Unless you have a crystal ball, you need to make a best guess! Once this
best guess is saved in the Baseline you have a comparison for progress
later. Your best guess needs to include some basic risk management for the
Task.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top