I make project schedule with Project Prof. 2007, after mapping local resouce
to server resource, saving to server and publish, and then login in to the
server, I found that all task which I assigned to other resouce on the
schedule were all in my task list. what's wrong? what can I do if I want to
auto assign task to others.
BTW: the accounts & resource on Project Server are synchronizated from
Active Directory's same groups.