L
letapia
This is for Project Server 2007.
Very simple escenario: 2 projects, 1 activity of 2 weeks duration each, 1
enterprise resource assigned to both projects, 1 enterprise base calendar on
server. I want to assign the resource to work in project A during weekend
without affecting scheduled work on Project B. I've tried this:
1) Change the enterprise base calendar => it changes both projects (duh!
obvious)
2) Change the enterprise resource calendar => it changes both projects (duh!
obvious)
3) Allow local base calendars, change local base calendar to make weekend
workable (sorry my english) on Project A => No work assigned during weekend
as the resource calendar is still the base enterprise calendar.
That's it. here I'm stuck!!!. In summary I want to make an exception for the
resource availability, but only for one project. This is the typical "Go
Live" activity for a DBA who also participates in several other projects.
Very simple escenario: 2 projects, 1 activity of 2 weeks duration each, 1
enterprise resource assigned to both projects, 1 enterprise base calendar on
server. I want to assign the resource to work in project A during weekend
without affecting scheduled work on Project B. I've tried this:
1) Change the enterprise base calendar => it changes both projects (duh!
obvious)
2) Change the enterprise resource calendar => it changes both projects (duh!
obvious)
3) Allow local base calendars, change local base calendar to make weekend
workable (sorry my english) on Project A => No work assigned during weekend
as the resource calendar is still the base enterprise calendar.
That's it. here I'm stuck!!!. In summary I want to make an exception for the
resource availability, but only for one project. This is the typical "Go
Live" activity for a DBA who also participates in several other projects.