M
mark
I have a 400 line project plan i've spent literally weeks
painstakingly manually adjusting and checking, rechecking predecessor
relationships. I am familiar with and use frequently the Excel "AUDIT"
functions which allow me to quicky find where a cell has been used, or
which other cells use the current cell. This function would be a very
handy way to validate a project plan. Manually scrolling up and down,
expanding and contracting summary tasks looking at task numbers to
validate 5 predecessors is both cumbersome and very error prone. It
would be handy to select a task and click 'show predecessor' and have
all direct predecessors highlighted, or selected, or put into a text
file for a report.
Any suggestions would be appreciated. I'm using project 2003.
painstakingly manually adjusting and checking, rechecking predecessor
relationships. I am familiar with and use frequently the Excel "AUDIT"
functions which allow me to quicky find where a cell has been used, or
which other cells use the current cell. This function would be a very
handy way to validate a project plan. Manually scrolling up and down,
expanding and contracting summary tasks looking at task numbers to
validate 5 predecessors is both cumbersome and very error prone. It
would be handy to select a task and click 'show predecessor' and have
all direct predecessors highlighted, or selected, or put into a text
file for a report.
Any suggestions would be appreciated. I'm using project 2003.