B
boxta
HI guys, I am using Project 2007, and I am not able to get exactly what
I need.
Currently, in the resource information, one can assign 5 rate tables
per resource (A-E). However, I have a requirement to assign up to 20
different rates to an individual. I am not able to get around with it.
Hence, am not able to get the actual cost estimate for projects
Does anyone have any thoughts?
I am trying a few workarounds:
By pass the rate table, and create a custom field with look up values
in Project Plan, I can get the field to hold as many rates as I can, but
ultimately you can only have 1 rate per row, which means 1 rate per task
.. When you have multiple resources to a task, then i gets tricky.
I am also thinking about creating different resources for the same
person. So say for mike, he has 20 different projects, hence 20
different rates potentially. I will create mike_1, mike_2, mike_3 and
mike_4. Each carry 5 rates, total of 20. This would however be quite
confusing as one would need to remember which project is assigned to
which mike's profile.
I am out of idea. Any thoughts would be appreciated!
thanks
I need.
Currently, in the resource information, one can assign 5 rate tables
per resource (A-E). However, I have a requirement to assign up to 20
different rates to an individual. I am not able to get around with it.
Hence, am not able to get the actual cost estimate for projects
Does anyone have any thoughts?
I am trying a few workarounds:
By pass the rate table, and create a custom field with look up values
in Project Plan, I can get the field to hold as many rates as I can, but
ultimately you can only have 1 rate per row, which means 1 rate per task
.. When you have multiple resources to a task, then i gets tricky.
I am also thinking about creating different resources for the same
person. So say for mike, he has 20 different projects, hence 20
different rates potentially. I will create mike_1, mike_2, mike_3 and
mike_4. Each carry 5 rates, total of 20. This would however be quite
confusing as one would need to remember which project is assigned to
which mike's profile.
I am out of idea. Any thoughts would be appreciated!
thanks