How to calculate & display the % of tasks baselined for a project
JavaScript is disabled. For a better experience, please enable JavaScript in your browser before proceeding.
Reply to thread
Message
[QUOTE="Caroline Gormley, PMP, MCT, post: 5006664"] Yes, it was something very simple! I'd set up my "Percent Baselined Tasks" field as a Number field when it should have been a Text field. The macro is working fine now. Thanks again. [/QUOTE]