B
Bhavtosh
hi all,
im ok the way ms project does the calculation of days for various tasks.
but at time for small workout is there a way where i can achieve scenario
where i enter task name and a duration in days and dont set the dates [start
and end]
After entering 5 tasks and i just want to see the total days as a total
under duration column? i want to do the same as what we do in ms excel using
function SUM()
also how can i share a screen snapshot in this forum to clarify my question?
im ok the way ms project does the calculation of days for various tasks.
but at time for small workout is there a way where i can achieve scenario
where i enter task name and a duration in days and dont set the dates [start
and end]
After entering 5 tasks and i just want to see the total days as a total
under duration column? i want to do the same as what we do in ms excel using
function SUM()
also how can i share a screen snapshot in this forum to clarify my question?