How to cancel task in Microsoft Project without deletion it ?

  • Thread starter Mohamed El-Gammal
  • Start date
M

Mohamed El-Gammal

Dears
I need to cancel a task in Microsoft Project file but without deleting it.
what is the best way to do this?
 
M

Mike Glen

However, I seem to remember somewhere that this feature will only be available in the Project Pro version.

Mike Glen
Project MVP

Trevor's response is correct for Project 2007 and earlier. Project 2010
includes a new feature which allows inactivating tasks which keeps them
visible but does not include them in the regular schedule calculations.

You can see it in a webcast here:
http://zo-d.com/blog/archives/microsoft-project-2010/project-2010-tips-and-tricks-webcast.html

-Jack
 
J

JulieS

You are correct, Mike. Inactive tasks are only available in
Professional, not Standard versions

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 