R
Raymond Lardenoije
Some of my clients are building contractors. They are used to have
"un-workable days" in the winter (for example when it is freezing you can not
lay bricks or pour concrete outside). In The Netherlands there are guidelines
for how much "un-workable days" a contractor can expect in a certain year.
And they would like to see a time-table / calendar that for example shows 15
work-days in January instead of the normal 20-22 work-days. However, they do
not want to set the exact "un-workable days" in advance (because then clients
and subcontractors will not show up even when it is not freezing).
Because they know to expect approximately 5-7 days of frost they would like
their project-plan to show those days, without specifying the exact days. So
instead of a calendar "sunday january 1 , monday january 2, etc" they would
like a calendar like "january 1st workday, january 2nd workday".
Is something like that at all possible ?
"un-workable days" in the winter (for example when it is freezing you can not
lay bricks or pour concrete outside). In The Netherlands there are guidelines
for how much "un-workable days" a contractor can expect in a certain year.
And they would like to see a time-table / calendar that for example shows 15
work-days in January instead of the normal 20-22 work-days. However, they do
not want to set the exact "un-workable days" in advance (because then clients
and subcontractors will not show up even when it is not freezing).
Because they know to expect approximately 5-7 days of frost they would like
their project-plan to show those days, without specifying the exact days. So
instead of a calendar "sunday january 1 , monday january 2, etc" they would
like a calendar like "january 1st workday, january 2nd workday".
Is something like that at all possible ?