Hi,
We are using MS Project 2003 non enterprise in our organization.Now
the Project Manager is changed so how can we change the Project Manager so
that the updates are received by new manager.Project->publish->republish
assignment changes the owner but not Project Manager and all the updates are
reverted to old PM's id.
Our is Non enterprise Project so kindly reply back considering this,,,,,,,