How to change Project Manager of Non Enterprise Project

N

Nids

Hi,
We are using MS Project 2003 non enterprise in our organization.Now
the Project Manager is changed so how can we change the Project Manager so
that the updates are received by new manager.Project->publish->republish
assignment changes the owner but not Project Manager and all the updates are
reverted to old PM's id.
Our is Non enterprise Project so kindly reply back considering this,,,,,,,
 
J

Jan De Messemaeker

Hi,

If you are not using the enterprise featurs there is no such thing as
publishiing!
Which one is it? Project Server or not Project Server?
 
N

Nids

HI Jan
It is Project Server but we have disabled enterprise features because
we were facing some problems with that.Now we are using Project Server with
non enterprise features.So any idea about it??
--
Thanks & Regards,
Nids


Jan De Messemaeker said:
Hi,

If you are not using the enterprise featurs there is no such thing as
publishiing!
Which one is it? Project Server or not Project Server?
 
J

Jan De Messemaeker

Hi,

Sorry to have kept you on the wrong assumption that it was not server (which
I know very little of)
You may getr more focused resporce in
microsoft.public.project.server

--
Jan De Messemaeker
Microsoft Project MVP
+32 495 300 620
http://users.online.be/prom-ade
Nids said:
HI Jan
It is Project Server but we have disabled enterprise features because
we were facing some problems with that.Now we are using Project Server
with
non enterprise features.So any idea about it??
 

Ask a Question