how to change remaining work format on timesheet

F

Fabrício Costa - Brazil.

Hi Gail, I'm having the same problem. I think it's not possivel. The aswers
before appointed to a solution where we needed to edit the Web Part from
PWA. But is possible to change to hours just in"My Tasks" web part.
I don't understand why we have this option in "My Tasks" and don't have to
others that I consider more important to control project progress.
 
D

Dale Howard [MVP]

Fabricio --

Unfortunately, you cannot change the format of the Remaining Work field from
Days to Hours in the My Timesheet page. Hope this helps.




"Fabrício Costa - Brazil." <Fabrício Costa -
(e-mail address removed)> wrote in message
news:[email protected]...
 