How to change the resource Type

R

Robert

Hello,
It seems that, once the resource has been created, it's not possible to
change its Type : Work, Material or Cost.
I tried both in PWA and Project Pro : Checked out Eenterprise Resource Pool.
Is it right ?
Thanks
 
B

Ben Howard

Hi Robert, i've never tried it, but it would make sense that you cannot
change them as the resource type has an effect on the cost calculation?

Also, a resource is unlikely to change it's type.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top