How to change the status manager of all tasks of project

S

Sam

By mistake i have publish the project with the web access .
now the tasks update request is routing to my "Tasks Update" page.
When i open the project in project professional and open the column of
"Status Manager ".
see the "Status Manager" has changed and my name is there .
How i can change the all tasks of project "Status manager" with the project
manager name with the single click. then all tasks update requests must route
to project manager.

Pls reply me soon
 
B

Ben Howard

Hi Sam,
the PM must open project, and then he can change the status manager field.
He can copy the field down (highlight and CTRL-D)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top