How to change work schedule for one task in a project?

M

Mimi

Does anyone know if/how I can change the work scheduled for one or several
tasks within a project in Project2000? This is only required for one set of
tasks which must take place over the weekend, while the remaining tasks all
follow the standard Mon - Fri standard work week?

Any ideas?

Thanks.
 
M

Mike Glen

Hi Mimi,

Welcome to this Microsoft Project newsgroup :)

Create a calendar for the weekend only and for the tasks concerned, in Task
Information, select that calendar for that task.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top