How to change work without affecting duration

D

David Morrison

I have a number of tasks that have longer durations than work. I've already
set the duration but when I set the work Project tries to change the
duration to match. I presents the option of decreasing task duration or
keeping duration the same while reducing work. The default seems to be
decreasing duration but I want it to default leaving duration the same. Can
this default be changed anywhere? I can manually override it but that's a
lot of work.
 
M

Mike Glen

Hi David,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series of Microsoft Project lessons in
the TechTrax ezine, particularly Lesson 11 – Task Types - at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
S

Steve House

Mark the task "fixed duration" before editing the work and Project will hold
duration constant, recalculating the resource assignment percentage instead.
 
D

David Morrison

Thanks! That did the trick.

Mike Glen said:
Hi David,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series of Microsoft Project lessons in
the TechTrax ezine, particularly Lesson 11 - Task Types - at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top