I have an MS Project 2003 schedule that I'm publishing to PS 2003. Project
Server is setup Tracking Settings:
- Hours of work done per day or per week: Resources report the hours worked
on each task during each time period.
- Managed Periods
I've assigned tasks to resources....and the tasks have "remaining work". If
I go into the project schedule and set "remaining work" to 0 then it shows "%
work complete" at 100% and shows the task complete on the resource PWA
tasklist.
Is there a way to close a task so a resource (that has submitted time
against the task) cannot continue to submit time against the task?
Server is setup Tracking Settings:
- Hours of work done per day or per week: Resources report the hours worked
on each task during each time period.
- Managed Periods
I've assigned tasks to resources....and the tasks have "remaining work". If
I go into the project schedule and set "remaining work" to 0 then it shows "%
work complete" at 100% and shows the task complete on the resource PWA
tasklist.
Is there a way to close a task so a resource (that has submitted time
against the task) cannot continue to submit time against the task?