How to close projects ?

N

Newbie

Hello,

My resources are assigned on 4 projects. 3 of these projects are closed : I
set the "Remaining Work" of every task to zero. I saved and closed every old
project.
But in the "Resource Usage" view of the 4th project, each resource has some
remaining work on the closed project.

What did I missed ?

Thanks for help.

Newbie.
 
C

Cool Timbers

Did you publish the project plan of the three projects?

I have noticed some incorrect remaing work in the Resource Usage View.
You can open all four projects while in one instance of Project Pro
2003, and then check the resource usage view, and you should get
accurate information.
 