How can a project manager achieve that a project member can report no more
time on an activity? Suppose the project member was scheduled to do 100 hours
and has reported 80. After progress the PM decides to set the remaining work
to 0 and republishes the assignment. But in PWA the resource is still able to
report time on this activity…..