J
Jean-Luc
I would like to use (pessimistic, realistic, optimistic)
estimates.
MSP2000 offers me the 'pert computation', which isn't very
useful as it sort of cumulates all pessimistic data - I
don't want to be that conservative.
Based on the realistic estimates, I want to use the CP
(Critical Path) and the estimated project end date. Then,
I would like to get the CP's Standard Deviation to
estimate the total project slack I can justify - in order
to meet stakeholder expectations to deliver with 95% of
probability (so, working at mean + 2 standar deviations).
How can I compute the CP Standard deviation?
estimates.
MSP2000 offers me the 'pert computation', which isn't very
useful as it sort of cumulates all pessimistic data - I
don't want to be that conservative.
Based on the realistic estimates, I want to use the CP
(Critical Path) and the estimated project end date. Then,
I would like to get the CP's Standard Deviation to
estimate the total project slack I can justify - in order
to meet stakeholder expectations to deliver with 95% of
probability (so, working at mean + 2 standar deviations).
How can I compute the CP Standard deviation?