How to configure Gantt bars in the Gantt Chart formats page

G

Gil Sturgeon

Is it possible to change what determins when a Gantt bar starts and ends? If
so how do you do it?
 
D

Dale Howard [MVP]

Gil --

By default, Microsoft Project draws each Gantt bar from the Start date to
the Finish date of each task. You can double-click anywhere in the white
part of the Gantt Chart to see this definition in the Bar Styles dialog, and
to change it if you need to do so. Hope this helps.
 
G

Gil Sturgeon

Dale,
Thanks for the reply. I was not clear when I wrote my question.

I am trying to customize the Gantt bars that are dispalyed in the Projects
Center on Web Access. I am working in the Admin Center - Customize Project
Web Access - Gantt Chart formats page.

I was hoping Web Access offered the same type of control over the start and
end of bars that is found in the Bar Styles dialog window in Project Pro but
I have not been able to find that type of control.

Any suggestions?
 