S
SteveLP
Using Project Server 2007
I’m trying to create a Critical Path for a Project Plan. I understand that
the default for Project is that all tasks are critical tasks when they are
created. Most of my tasks are predecessors of the tasks above and all my
tasks have Constraint Type of “As Soon As Possibleâ€.
How do I create Total Slack value to be positive on certain tasks while
keeping Total Slack of 0 for the Critical Path Tasks?
I don’t have a Deadline set for any of my tasks nor a Constraint date.
I’m trying to understand how the Total Slack field is affected when
selecting a Deadline, Constraint Date or Constraint Type.
Thanks in advance,
SteveLP
I’m trying to create a Critical Path for a Project Plan. I understand that
the default for Project is that all tasks are critical tasks when they are
created. Most of my tasks are predecessors of the tasks above and all my
tasks have Constraint Type of “As Soon As Possibleâ€.
How do I create Total Slack value to be positive on certain tasks while
keeping Total Slack of 0 for the Critical Path Tasks?
I don’t have a Deadline set for any of my tasks nor a Constraint date.
I’m trying to understand how the Total Slack field is affected when
selecting a Deadline, Constraint Date or Constraint Type.
Thanks in advance,
SteveLP