Thanks Julie.
I will try to re-assign those budgets and see how it goes. I also
have a
look at the printer issue and get back to you with the update.
Thanks again a million ;-)
:
Hi,
My comments are inline.
message
Hi Julie,
1. What do you mean by update a printer drive? I have been
using
the
printer
as normal ;-). I do also select the way you advised
File>Print>set
date range
preview. and it comes up all the projects and thier tasks
(basically
the
whole master project). I am not sure I know by what you mean
of
updating the
printer ;-(
[Julie] Printer drivers are selected in the Control panel and
project
is a bit picky about having outdated printer drivers or printers
which
do not match the physical printer you are printing to. Try
going
out
to your printer manufacturer's website and see what the latest
driver
is for the printer make and model you are running.
I'm still not seeing what you are in a master project. I
display
the
Resource Usage view, set the range I want to see in the File >
Print
command. Sorry, I'm not sure what is causing the problem. I've
experimented with assigning resources to very long duration
tasks
(thinking that may cause some trouble) but I still seem to be
able
to
print just a selected date range of the Resource Usage view.
2. As all my projects have different budget-labour and cost
values
so when i
used the resource pool it has created a new budgte-labour and
new
budget-cost
everytime my value was different (well, i think that is what
it
did
anyway).
So therefore in my resource pool now 30 of each are present
Should I
delete
them all and just allocate from the resource pool to each
project
from
scratch? Would'nt that cause confusion when I want to review
each
project's
own budget-labour and budget-cost?
[Julie] Odd again
I have three different budget resources
and
each resource is assigned to several project summary tasks.
When
viewing the Resource Usage view, I only see one of each resource
with
the assignments for each underneath. Once you assign the budget
resources to the project summary tasks, you manually go in and
enter
the Budget Work or Budget Cost for each budget resource. You
don't
assign costs until after you've made the assignments. Help does
a
pretty good job stepping through this. See the topic "Create a
budget
for your project."
Many many thanks again
[Julie] - You're very welcome.
B.horvath
:
Hello,
My comments are inline.
Julie
message
Hi Julie,
I have managed to do all the 30 projects by asigning them
to
my
newly
created resource pool and created a master project as well.
Thank
you for
that.
[Julie] You're welcome. Glad to have helped.
I have a couple of questions.
1. When I look at the Resource Usage (as you have suggested
to
see
who does
what, when and for long) I can see all the tasks and
projects,
date,
time,
etc. When I want to print I can select by date range which
is
what I
need,
however when I chose for example one week starting from
this
week
to
next
week and I go to preview, it still includes tasks from
2006,
2007,
so
basically the everything not the chosen week. Any idea?
[Julie] Hmmm. A quick test from a master project file
created
from a
pool works well for me. If I choose File > Print and set the
date
range in the Print dialog box for a two week period in the
middle
of
the project, the preview shows just that two week period.
How
are
you
selecting the print range? Make sure your printer drivers
are
also
up
to date, Project is very picky about printer drivers.
2. As some our prohects have budgets in labour and some has
costs, I
have
created a Budget-Labour and a Budget-Cost which I have
allocated
to
it's
relevant project and it shows how much we allocated for
each
project
in
labour or/and cost.
When I look at the master project I have 30 times the
Budget-Labour
and 30
times the Budget-cost. Is this correct or should have been
only
one
of each
just as the resources?
[Julie] Did you define the Budget-Labour and Budget-Costs in
the
resource pool and assign from there? Did you add the
resources
to
the
project summary tasks as the help screens note?
I hope this helps.
Julie
Many thanks in advance ;-)
B.Horvath
:
You're most welcome. Glad to have helped and thanks for
the
feedback.
Have a good weekend.
Julie
message
Hi Julie,
Wow, I think I have just done it. Great,Thanks. I will
have
to
revise with
my actual projects (as i was using a test one in case i
mess
it
up),
so it
will take me a couple of hours, but I will get back to
you
on
Monday
and let
you know how it went. I hope it will look like what I
had
in
mind.
Fingers
crossed.
Thanks again so much
Kindly,
B.Horvath
:
Hello,
You're not being a pain at all
You should be creating the master project file by
opening
the
resource
pool and selecting the 3rd option "Open resource pool
read/write
and
all other project files into a new master project...."
No
need
to
insert the individual project files into a master --
the
pool
will
help you create it.
I hope this helps.
Julie
in
message
Hi Julie,
Thanks again for the quick response.
I have done what you said by creating a resource pool
and i
have
assigned it
to my projects individually, which went ok. Once I
have
done
this
with all
the seperate projects and inserted them in a new
master
projects
again.
However I can still see all the resources one after
the
other
30
times. Where
am I going wrong? (I thought once they all have the
same
recources
from the
same resource pool the master project would be only
showing
the
5
resources
once).
What am I missing? ;-) Sorry to be a pain.
Thanks in advance.
B.Horvath
:
Hello,
You're welcome for the assistance and thanks for the
feedback.
Thanks for the additional information that you have
added
the
5
resources to each project file. I suggest creating
a
resource
pool
file to hold the information on your 5 resources and
then
sharing
the
pool file with your 30 projects. Luckily, it's not
as
hard
as
it