T
Triasp
I have a Board that only meets twice a month (every 1st and 3rd Thursday), so
I created a recurring task. However, I do not want my project to come up at
every Board meeting. I want my project to be on the agenda of the next
available Board meeting after a certain task has been completed.
For instance, Task A was scheduled to be on the 11/4 meeting, but the
timeframe changed so that Task A is not scheduled to be completed until 11/7.
I wanted Task A to be scheduled on the 11/18 meeting, instead of the 11/4
meeting.
I tried doing a Finish to Start link between Task A and the Board meetings,
and Project scheduled the Board meeting on the day that Task A is scheduled
to be completed on (11/7), instead of the next schedule meeting (11/18).
In Project, is there a way to tell the calendar to do this?
Thanks
I created a recurring task. However, I do not want my project to come up at
every Board meeting. I want my project to be on the agenda of the next
available Board meeting after a certain task has been completed.
For instance, Task A was scheduled to be on the 11/4 meeting, but the
timeframe changed so that Task A is not scheduled to be completed until 11/7.
I wanted Task A to be scheduled on the 11/18 meeting, instead of the 11/4
meeting.
I tried doing a Finish to Start link between Task A and the Board meetings,
and Project scheduled the Board meeting on the day that Task A is scheduled
to be completed on (11/7), instead of the next schedule meeting (11/18).
In Project, is there a way to tell the calendar to do this?
Thanks